Bathroom Remodel 2015
Photos represents tasks pretty much in the order they occurred from April 6 thru July 15.
Also included are project distractions (e.g. holidays, looking for a nail, and a broken sprinkler).
Photos at the bottom of the page represent the finished product.
To Do as of 7-15-2015:
(1) Floating shelves above the toilet.
(2) Glass Shower door.
Attic walkway raised 2 inches to accommodate the height of new exaust fan. Shown without decking.
171 Tiles (18 floor, 128 wall, 5 border, 20 curb)
149 horizontal and vertical cuts
toilet with temp $25 shelves
RBS Memorial Shower
temp shower curtain. Clear so we can see the pretty shower.